TWO-BLOCK SECTION
OF CUMBERLAND AVENUE TO REOPEN FOUR
DAYS AHEAD OF SCHEDULE
By 5 p.m. today, a temporarily closed two-block section of Cumberland Avenue
between 17th and 19th streets will reopen.
Since Tuesday, crews have been installing an underground electrical line
beneath the four lanes of Cumberland Avenue. The line is 12 feet below the
road, and burying the line allows for the removal of overhead power lines along
Cumberland Avenue.
The project had been scheduled to be completed by 5 p.m. on Tuesday, Jan. 5,
2016. But the earlier-than-anticipated street reopening means that it will be
easier for New Year’s Eve patrons of Cumberland Avenue restaurants to access
parking.
“Cumberland Avenue has remained open for business from Day 1, since the
two-year Cumberland reconstruction project started back in April,” said Anne
Wallace, the City’s Deputy Director of Redevelopment.
“What better way to ring in the new year than by patronizing a favorite
Cumberland restaurant tonight? Or enjoy the game-day festivities and special
menu items on New Year’s Day, with the Vols playing in the Outback Bowl. Go Big
Orange!”
Crews will be paving the section of Cumberland Avenue between
17th and 19th streets next Monday and Tuesday, Jan. 4-5,
but traffic will be temporarily shifted with no long-term lane closures.
The relocation and upgrade of electric infrastructure is
part of the City’s overall $17 million reconstruction of the corridor.
Phase I work on
the western end of Cumberland, between the Alcoa Highway ramps and 22nd
Street, is completed – on time and under budget. Improving traffic flow was a
key objective of the Phase I work. Synchronized traffic flow at Metron Center Way
and a dedicated turn lane onto northbound Alcoa Highway have lessened
decades-long issues with congestion.
Phase II work
is underway in the section of Cumberland Avenue between 22nd and 17th
streets. Scheduled to be completed in August 2017,
the reconstruction will change the existing four-lane street on the
eastern end of the corridor to a three-lane cross section with a raised median
and left-turn lanes at intersections between 22nd Street and 17th
Street.
In both the Phase I and Phase II
work, Cumberland Avenue sidewalks are being widened, and utility infrastructure
relocated and upgraded, to create a more attractive, safer, pedestrian-friendly
corridor.
Meanwhile,
motorists next week should anticipate new street closures associated with the
Phase II work:
- From 6 a.m. to 6 p.m.
Sunday, Jan. 3, two lanes in the 1500 block of Cumberland Avenue – between
Volunteer Boulevard and Philip Fulmer Way – will be closed while KUB installs
new sewer system infrastructure. One eastbound and one westbound lane will
remain open.
- From 6 a.m. Monday, Jan.
4, until 6 p.m. Saturday, Jan. 9, a section of South 18th Street
between Cumberland and the alley north of Lake Avenue will be closed to allow
crews to install an electrical duct bank.
- From Monday, Jan. 4,
through Wednesday, Jan. 6, sections of North 18th and 19th
streets, from Cumberland to the alley, will be closed to accommodate work
upgrading the sewer system.
RIBBON CUTTING TO CELEBRATE COMPLETION OF PHASE I, CUMBERLAND AVENUE RECONSTRUCTION
What: Ribbon-cutting to
celebrate the completion of Phase I of the reconstruction of Cumberland Avenue
When: 4 p.m. Wednesday, Jan.
6, 2016
Where: Grassy area just
north of the Three Rivers Rambler depot, 2560 University Commons Way; parking
available in the lot south of the depot
Who: Knoxville Mayor
Madeline Rogero, 1st District City Councilman Nick Pavlis and other
Council members, Cumberland Avenue Merchants Association members, City of
Knoxville Office of Redevelopment staff, Engineering Department staff,
representatives of Knoxville Utilities Board, and representatives of Vaughn
& Melton Consulting Engineers and Southern Constructors, Inc.
Phase I of the
reconstruction of Cumberland Avenue, between the Alcoa Highway ramps and 22nd
Street, has ended – on time and under budget. Improving traffic flow was a key
objective of the Phase I work. Synchronized traffic flow at Metron Center Way
and a dedicated turn lane onto northbound Alcoa Highway have lessened
decades-long issues with congestion.
Phase II work
is underway in the section of Cumberland Avenue between 22nd and 17th
streets. Scheduled to be completed in August 2017,
the reconstruction will change the existing four-lane street on the
eastern end of the corridor to a three-lane cross section with a raised median
and left-turn lanes at intersections.
In both the Phase I and Phase II
work, Cumberland Avenue sidewalks are being widened, and utility infrastructure
relocated and upgraded, to create a more attractive, safer, pedestrian-friendly
corridor.
Anyone needing a disability
accommodation to attend the Jan. 6 ribbon-cutting should contact the City’s ADA
Coordinator, Stephanie Cook, at scook@knoxvilletn.gov or 865-215-2034. For an English interpreter,
contact Kim Scarborough at kscarborough@knoxvilletn.gov
or 865-215-2029.
As always, thank you for your interest in all things pertaining to Cumberland Avenue - have a safe, fun-filled and happy new year!
No comments:
Post a Comment