Thursday, December 31, 2015

December 31st Update and Happy New Year!

TWO-BLOCK SECTION OF CUMBERLAND AVENUE TO REOPEN FOUR DAYS AHEAD OF SCHEDULE

                By 5 p.m. today, a temporarily closed two-block section of Cumberland Avenue between 17th and 19th streets will reopen.

                Since Tuesday, crews have been installing an underground electrical line beneath the four lanes of Cumberland Avenue. The line is 12 feet below the road, and burying the line allows for the removal of overhead power lines along Cumberland Avenue.

                The project had been scheduled to be completed by 5 p.m. on Tuesday, Jan. 5, 2016. But the earlier-than-anticipated street reopening means that it will be easier for New Year’s Eve patrons of Cumberland Avenue restaurants to access parking.

                “Cumberland Avenue has remained open for business from Day 1, since the two-year Cumberland reconstruction project started back in April,” said Anne Wallace, the City’s Deputy Director of Redevelopment.

                “What better way to ring in the new year than by patronizing a favorite Cumberland restaurant tonight? Or enjoy the game-day festivities and special menu items on New Year’s Day, with the Vols playing in the Outback Bowl. Go Big Orange!”

Crews will be paving the section of Cumberland Avenue between 17th and 19th streets next Monday and Tuesday, Jan. 4-5, but traffic will be temporarily shifted with no long-term lane closures.

The relocation and upgrade of electric infrastructure is part of the City’s overall $17 million reconstruction of the corridor.

Phase I work on the western end of Cumberland, between the Alcoa Highway ramps and 22nd Street, is completed – on time and under budget. Improving traffic flow was a key objective of the Phase I work. Synchronized traffic flow at Metron Center Way and a dedicated turn lane onto northbound Alcoa Highway have lessened decades-long issues with congestion.

Phase II work is underway in the section of Cumberland Avenue between 22nd and 17th streets. Scheduled to be completed in August 2017, the reconstruction will change the existing four-lane street on the eastern end of the corridor to a three-lane cross section with a raised median and left-turn lanes at intersections between 22nd Street and 17th Street.

In both the Phase I and Phase II work, Cumberland Avenue sidewalks are being widened, and utility infrastructure relocated and upgraded, to create a more attractive, safer, pedestrian-friendly corridor.

Meanwhile, motorists next week should anticipate new street closures associated with the Phase II work:

-  From 6 a.m. to 6 p.m. Sunday, Jan. 3, two lanes in the 1500 block of Cumberland Avenue – between Volunteer Boulevard and Philip Fulmer Way – will be closed while KUB installs new sewer system infrastructure. One eastbound and one westbound lane will remain open.

-  From 6 a.m. Monday, Jan. 4, until 6 p.m. Saturday, Jan. 9, a section of South 18th Street between Cumberland and the alley north of Lake Avenue will be closed to allow crews to install an electrical duct bank.

-  From Monday, Jan. 4, through Wednesday, Jan. 6, sections of North 18th and 19th streets, from Cumberland to the alley, will be closed to accommodate work upgrading the sewer system.


More information is available at www.CumberlandConnect.com, on the Cumberland Connect Facebook page, facebook.com/CumberlandConnect, and on the Cumberland Connect phone app.

RIBBON CUTTING TO CELEBRATE COMPLETION OF PHASE I, CUMBERLAND AVENUE RECONSTRUCTION

What: Ribbon-cutting to celebrate the completion of Phase I of the reconstruction of Cumberland Avenue

When: 4 p.m. Wednesday, Jan. 6, 2016

Where: Grassy area just north of the Three Rivers Rambler depot, 2560 University Commons Way; parking available in the lot south of the depot

Who: Knoxville Mayor Madeline Rogero, 1st District City Councilman Nick Pavlis and other Council members, Cumberland Avenue Merchants Association members, City of Knoxville Office of Redevelopment staff, Engineering Department staff, representatives of Knoxville Utilities Board, and representatives of Vaughn & Melton Consulting Engineers and Southern Constructors, Inc.


Phase I of the reconstruction of Cumberland Avenue, between the Alcoa Highway ramps and 22nd Street, has ended – on time and under budget. Improving traffic flow was a key objective of the Phase I work. Synchronized traffic flow at Metron Center Way and a dedicated turn lane onto northbound Alcoa Highway have lessened decades-long issues with congestion.

Phase II work is underway in the section of Cumberland Avenue between 22nd and 17th streets. Scheduled to be completed in August 2017, the reconstruction will change the existing four-lane street on the eastern end of the corridor to a three-lane cross section with a raised median and left-turn lanes at intersections.

In both the Phase I and Phase II work, Cumberland Avenue sidewalks are being widened, and utility infrastructure relocated and upgraded, to create a more attractive, safer, pedestrian-friendly corridor.


Anyone needing a disability accommodation to attend the Jan. 6 ribbon-cutting should contact the City’s ADA Coordinator, Stephanie Cook, at scook@knoxvilletn.gov or 865-215-2034. For an English interpreter, contact Kim Scarborough at kscarborough@knoxvilletn.gov or 865-215-2029. 

As always, thank you for your interest in all things pertaining to Cumberland Avenue - have a safe, fun-filled and happy new year!

Monday, December 28, 2015

Construction Update December 28th


Construction Update for 18th Street Electrical Crossing

Due to the heavy rain in the forecast for tonight the decision has been made to delay start of the excavation work to cross Cumberland at 18th until tomorrow morning, Tuesday, December 29. Cumberland will remain open to traffic today. 


More information about the project is available at www.CumberlandConnect.com, on the Cumberland Connect Facebook page, facebook.com/CumberlandConnect, and on the Cumberland Connect phone app.

Thursday, December 24, 2015

December 24th Update

TWO BLOCKS OF CUMBERLAND AVE. TO BE CLOSED DEC. 28-JAN. 5

                Two blocks of Cumberland Avenue between 17th and 19th streets will be closed for eight days beginning Monday, Dec. 28, to allow for the installation of an underground electrical line.

                The closure is scheduled to begin at 6 a.m. on Dec. 28 and continue until 5 p.m. on Tuesday, Jan. 5, 2016. Vehicle traffic will be detoured to Clinch Avenue between 17th and 19th streets. Pedestrian access to businesses along Cumberland Avenue will be maintained throughout.

The electrical line will carry power from a Knoxville Utilities Board substation at Dale Avenue to the Cumberland Avenue area and beyond. It will allow the removal of overhead power lines along Cumberland Avenue, part of the City’s overall $17 million reconstruction of the corridor.

The Cumberland Avenue project, scheduled to be completed in August 2017, will change the existing four-lane street on the eastern end of the corridor to a three-lane cross section with a raised median and left-turn lanes at intersections between 22nd Street and 17th Street.

Phase I work on the western end of Cumberland, between the Alcoa Highway ramps and 22nd Street, is coming to an end – on time and on budget. Phase II is under way.


                More information about the project is available at www.CumberlandConnect.com, on the Cumberland Connect Facebook page, facebook.com/CumberlandConnect, and on the Cumberland Connect phone app.

Cumberland Avenue Merchants Association (CAMA) - Monthly Meeting
Date: Wednesday, January 6
Time: 3:00 - 4:00 pm 
Location: Copper Cellar, 1807 Cumberland Avenue

What: The merchants and other interested stakeholders meet to discuss items of interest or concern and get updates on the City's Cumberland Avenue Corridor Project.

Parking: Available parking is located at Copper Cellar.